Quick summary

  • Lisk SDK v6.0.0 continues development in preparation for the beta phase, with 10 issues closed in total
  • Lisk DB v0.3.0 continues development of the "Optimize lisk-db for production" objective, with 4 issues closed in total
  • Lisk Docs continues to update the documentation for Lisk SDK v6.0.0, with 5 issues closed in total
  • Lisk Core v4.0.0 continues development in preparation for the beta phase, with 3 issues closed in total
  • Lisk Migrator v2.0.0 completes the planning of the "Update Lisk Core v4 migration strategy" objective, with development now due to start
  • Lisk Service v0.7.0 continues development in preparation for the beta phase, with 4 issues closed in total
  • Lisk Desktop v3.0.0 continues development of the "Change API to support Lisk SDK v6 API" and "Implement blockchain application transaction signing" objectives, with 10 issues closed in total
  • Lisk Mobile v3.0.0 continues development of the "Change API to support Lisk SDK v6 API" and "Prepare Lisk Mobile v3.0.0 for alpha" objectives, with 13 issues closed in total
  • Lisk DEX: Core v1.0.0 makes development progress, with the completion of the "Implement DEX module" objective
  • Lisk DEX: Service 1.0.0 continues the planning of the "Implement base micro-services for DEX module 1.0" objective
  • Lisk DEX: UI v1.0.0 starts the planning of the "Implement DEX information page (overview, pools, tokens)" objective

Lisk SDK

🗒️ The planning of Lisk SDK v6.0.0 objectives continues:

  • ✅ Support legacy blocks/transactions information (Completed stages: Design proposal, epic specification / Next stage: Development)

🏗️ The development of Lisk SDK v6.0.0 objectives continues:

  • ✅ Update flow of enabling generator - 1 issue closed this sprint / 8 issues closed in total
  • ✅ Resolve standalone issues (improvements/refactoring/others) - 5 issues closed in total
  • 🏗️ Prepare Lisk SDK v6.0.0 for beta - 3 issues closed this sprint / 3 issues added / 62 of 75 issues closed in total
  • 🏗️ Update modules with events and error handlings - 1 issue closed this sprint / 1 issue added / 12 of 17 issues closed in total
  • 🏗️ Introduce chain connector plugin - 2 issues added / 8 of 13 issues closed in total

Lisk DB

🏗️ The development of Lisk DB v0.3.0 objectives starts:

  • 🏗️ Optimize lisk-db for production - 4 issues closed this sprint / 4 of 20 issues closed in total

Lisk Docs

🏗️ The development of Lisk Docs for the Sapphire phase continues:

  • ✅ Resolve standalone issues (improvements/others) - 2 issues closed in total
  • 🏗️ Update Lisk SDK documentation for version 6 - 3 issues closed this sprint / 8 of 65 issues closed in total
  • 🏗️ Improve introduction contents - 3 of 9 issues closed in total

Lisk Core

🏗️ The development of Lisk Core v4.0.0 objectives continues:

  • 🏗️ Prepare Lisk Core v4.0.0 for beta - 3 issues closed this sprint / 6 of 12 issues closed in tota

Lisk Migrator

🗒️ The planning of Lisk Migrator v2.0.0 objectives concludes:

  • ✅ Update Lisk Core v4 migration strategy (Completed stages: Design proposal, epic specification / Next stage: Development)

Lisk Service

🏗️ The development of Lisk Service v0.7.0 objectives continues:

  • 🏗️ Prepare Lisk Service v0.7.0 for beta - 4 issues closed this sprint / 9 issues added / 5 of 25 issues closed in total

Lisk Desktop

🏗️ The development of Lisk Desktop v3.0.0 objectives continues:

  • 🏗️ Change API to support Lisk SDK v6 API - 7 issues closed this sprint / 7 issues added / 16 of 34 issues closed in total
  • 🏗️ Implement blockchain application transaction signing - 3 issues closed this sprint / 3 of 4 issues closed in total

Lisk Mobile

🗒️ The planning of Lisk Mobile v3.0.0 objectives continues:

  • ✅ Implement blockchain application transaction signing (Completed stage: Epic specification / Next stage: Development)

🏗️ The development of Lisk Mobile v3.0.0 objectives continues:

  • 🏗️ Change API to support Lisk SDK v6 API - 8 issues closed this sprint / 2 issues added / 16 of 19 issues closed in total
  • 🏗️ Prepare Lisk Mobile v3.0.0 for alpha - 5 issues closed this sprint / Awaiting new issues / 11 of 11 issues closed in total

Lisk DEX: Core

🗒️ The planning of Lisk DEX: Core v1.0.0 objectives continues:

  • 🗒️ Implement DEX rewards module (Completed stage: Knowledge sharing / Next stage: Requirements gathering)
  • 🗒️ Implement swap interaction (Current stage: Requirements gathering)

🏗️ The development of Lisk DEX: Core v1.0.0 objectives continues:

  • ✅ Implement DEX module - 4 issues closed this sprint / 2 issues removed / 12 issues closed in total
  • 🏗️ Implement liquidity provision - 7 issues todo

Lisk DEX: Service

🗒️ The planning of Lisk DEX: Service v1.0.0 objectives continues:

  • 🗒️ Implement base micro-services for DEX module 1.0 (Current stage: Requirements gathering)

Lisk DEX: UI

🗒️ The planning of Lisk DEX: UI v1.0.0 objectives continues:

  • 🗒️ Implement DEX information page (overview, pools, tokens) (Current stage: Requirements gathering)

🏗️ The development of Lisk DEX: UI v1.0.0 objectives continues:

  • 🏗️ Implement base user-interface for DEX module 1.0 - 8 of 12 issues closed in total

Lisk DEX

NOTE: The Lisk DEX (working title) is composed of the following component repositories: Lisk DEX: Core, Lisk DEX: Service, and Lisk DEX:UI. The Lisk DEX: Core being the equivalent of Lisk Core (the blockchain application backend). The Lisk DEX: Service being an extension of Lisk Service (the blockchain application middleware between Core and the UI). The Lisk DEX: UI being the blockchain application frontend. Going forward, the objectives of the Lisk DEX will be grouped accordingly (Core/Service/UI).

Initial goals for 2022:

  • ✅ Release Lisk Service v0.6.0, Lisk Desktop v2.2.0/v2.3.0, and Lisk Mobile v2.0.0 into production, thus completing the Emerald phase for these products
  • Complete the development of Lisk SDK v6.0.0 until the point of achieving "Base Interoperability", thus allowing alpha testing to start
  • Start the development of Lisk Core v4.0.0, Lisk Service v0.7.0, Lisk Desktop v3.0.0, and Lisk Mobile v3.0.0, thus commencing the implementation of the Sapphire roadmap phase (towards "Base - Interoperability")

Link to Message on Discord